Al Maktoum International Airport – Passenger Terminal Building Extension

  • Home
  • Completed

Scope of Work: Testing and Balancing of HVAC Systems
Location: Dubai, UAE
Client: Dubai Aviation Engineering Projects
Consultant:    Dar Al Handasah/ADPI
Main Contractor: Kumho/Ascon JV
MEP Contractor: Sungdo Engineering

About: The expansion project increased the terminal’s built-up area to approximately 1.57 million square feet, and adds new facilities to the arrival and departure areas. Expansions in the departure area include commercial zones and offices, as well as a new check-in hall with 64 counters and an additional ten counters for business class passengers. A new immigration hall with 55 border control counters is constructed for visa and passenger utilities. The expanded terminal now features a total of 24 boarding gates, seven baggage reclaim carousels, 104 check-in desks, and 2,542 parking spaces.